X
CONTACT US

CONTACT US

Please complete this short form to get in touch with a member of our team and we will get back to you as soon as we can.

X
NEWSLETTER

NEWSLETTER

Sign up to our newsletter by completing the form below.

We use cookies.

To make your experience the best it can be, we use cookies and similar technologies on our site. We need your permission to allow these technologies, which will maximise browsing experience. For more information on how we use cookies and how to change your cookie settings, please see our cookies and privacy policy.

Header image for the current page Futureproofing network connectivity for GP practices in Lincolnshire by optimising the data cabinet estate

Futureproofing network connectivity for GP practices in Lincolnshire by optimising the data cabinet estate

Share this page

NHS Arden & GEM’s IT Project and Programme Management and Delivery team secured funding and approval from Lincolnshire ICB to improve installation, use and maintenance of the data cabinet estate within local GP practices.

As a result of clear objectives, robust project management and forming strong collaborative working relationships with both the ICB and practice managers, the project was successfully delivered within budget and across 109 practices. Practice benefits include less network downtime, improved data cabinet security and maintainability, increased operational efficiency, and futureproofed capacity and connectivity.

The challenge

Summer 2022 was one of the hottest summers on record in the UK. This resulted in some devices in data cabinets overheating at GP practices, causing site network connectivity to go down and resulting in clinical issues due to staff being unable to access IT systems.

Over the past five years, the data cabinet estate in Lincolnshire’s 114 GP practices has also grown in use with multiple devices added into each data cabinet, and larger equipment generating more heat. Due to numerous third parties having access to the data cabinets, NHS Arden & GEM’s IT Project and Programme Management and Delivery (PPMD) team found an increasing amount of third-party equipment had been installed into the cabinets. This also led to varying cabling standards throughout.

Addressing these issues was imperative but any project work would need to minimise operational impact and fully involve GP practice managers, who were understandably apprehensive about any network downtime.

Our approach

On the back of these challenges, the PPMD team presented a proposal to Lincolnshire ICB for funding to form a project to undertake remedial action, including:

Minimising operational impact
An experienced network technician and technology facilitator, from the PPMD team, were appointed to lead the project, with assistance from a Project Manager and Project Support Officer.

The practice managers were consulted and asked to work in collaboration with the project team to ensure the optimal bespoke solution was implemented for each GP practice.

With a managed network outage required, a convenient window of downtime had to be scheduled to minimise operational impact. These ranged from lunchtime hours to evenings and weekends, dependant on the complexity and time of the requirement.

Engaging stakeholders
Regular project update meetings were put in place, along with the sharing of relevant project documentation, to ensure stakeholders were informed of progress. The Project Manager was able to escalate any issues that arose to the Project Board for a decision on how to proceed if required.

It was essential that practice managers were kept engaged in the process. This was achieved through open communication and ensuring that they understood the aim and the benefits of the project.

Data cabinet optimisation
Out of 114 practices, 109 were visited and data cabinets optimised. Hardware was repositioned and retired, a new cabling standard established and new shelving installed, which has created optimum airflow for cooling.

Three practices also had data cable infrastructure improvements made while 24 new network switches and 11 new data cabinets were installed. All unused equipment was sent to Arden & GEM’s logistics for use within the GP practices in the future. Photos and documentation were also updated for each GP practice which are held centrally to support future requirements.

The outcomes

As a result of clear objectives, robust project management and forming strong collaborative working relationships with both the ICB and practice managers, the project was successfully delivered within budget and across 96% of all practices.

Benefits of the project include:

Collectively, these benefits have resulted in less network downtime and increased operational efficiency for the GP practices.

 

"We have always been impressed by the professionalism of the IT team locally, both when providing us a remote and an on-site service.

We recently needed a refresh of our very untidy comms cabinet. As well as being aesthetically unpleasing, disorganised and untidy cabling can cause operational issues, obstruct the view of available ports and lead to tangled cabling. To address this issue required downtime for our network which would have been very inconvenient during working hours and we were offered an out of hours service instead. This meant no disruption to patients or staff.

The work took place at the time promised and was completed very efficiently within the advised timescale. We are very grateful for the swift and professional service that we received."

 Adrian Down, Managing Partner at Caythorpe and Ancaster Medical Practice

Find out more about our IT Services please follow this link